Summary of 7th Community Meeting

By Yvette Jarreau, President, FOSEL

May 20, 2026

 Boston Public Library, the City of Boston, and Utile hosted the seventh Community Meeting for the South End Branch on Tuesday, May 19th at Union Church on Columbus Ave.  After the presentation which included a revised project schedule, options for alley designs, proposed alley design and management, and Q&A’s, attendees were invited to walk to the alleys adjacent to the existing library to further understand the options that were presented. 

In addition to the many community members who attended at the church David Leonard, President of BPL was there with Priscilla Foley, Director of Neighborhood Services, Christina Jones, SE Library Branch Librarian, and Allison Ford, Manager of Major Projects and Operations. 

Sarah Sharpe, our Bay Village and South End Liaison from the Mayor’s Office kicked off the meeting, followed by Mohammed Missouri, Executive Director of City Neighborhood Services.  Also attending were Mayor Wu, City Councilor Ed Flynn, City Councilor Miniard Culpepper, Briana Millor, Chief of Community Engagement, and several people from the Public Facilities Department, as well as members of Public Works, including Dennis Roache, Superintendent.

In Mayor Wu’s welcome, she acknowledged our elected officials, Councilor Ed Flynn, Councilor Miniard Culpepper, and representatives from other Councilors’ offices.  She also conceded that this project has been delayed and is now prepared to go forward after receiving community input to the options being presented about how to manage the adjacent alleys.

Patricia (Trish) Cafferky, Deputy Chief of Operations, Mayor’s Office, presented the slides which began with the revised, estimated timeline for the building.  Completion of the design phase and updated construction documents will occur this spring/summer.  Simultaneously they plan on moving forward with the pre-qualification stage for hiring the contractor.  And by fall 2026 the project is planned to go out for bids, with the contracting phase happening in winter ‘26.  Construction should begin in the spring of 2027 and will take about 27 months.

After covering the timeline Trish shared the current street and alley configuration as well as service vehicle access.

Then Brett Bentson, Principal and Project Leader from Utile, explained each of three options for Alley #510 which are available here on slides 7-12 (with renderings) and then asked for input and questions from community members.  There were many ideas from the attendees which we hope the designers/planners will consider integrating into the final design.  Some of these ideas included: higher curbs to deter parking, no cobblestones, enforcement of No Parking (starting now, to get people used to it), and placing the transformer as close to the building on the alley side as possible, not enclosed by its own fence.

Mayor Wu asked for a preliminary show of hands for each of the options.  More people seemed to like Option 1 better than the other two options. 

However, this was before Trish Cafferky shared information about Alley 510 ownership, one half of which is owned by abutters and the other half by the Library/City.  To manage the increase in building size and resultant decrease in alley width, she presented the following operational changes for managing the alleys:

1. Private Alley 510 to become one-way to minimize conflicts.

2. Signage: Add No Stopping signage for fire access, public works services and neighborhood access.

3. Designation: Add the ‘Open to Public Travel’ designation to the alley. The alley is already open to public travel, as residents along Private Alley 529 pass through, but the designation adds clarity. 

After the presentation, Trish led a walk-through in the alley which had been laid out with temporary markers indicating the larger building and the footprint cutout which increases space for vehicles navigating the alley’s intersection with alley 529.  Community members asked questions and learned that an existing electrical transformer is located underground near the side of the current building, but a new one will need to be larger to accommodate increased electricity requirements for an all-electric branch and as a result will have to be moved closer to the Rutland Square end of the alley.  There are also considerations about the tree root systems that require placing the transformer further down the alley away from the building.

FOSEL hopes that people's concerns and suggestions will be integrated into the best possible approach for the neighborhood and the library.  We do not have an official position on the three options presented by the City on how to design and manage Alley #510 behind the library.  We feel this is best determined by the input from the people who live adjacent to the alley and the city officials with expertise on streets and city operations.

Because the project has been significantly delayed, we are pleased that it will move forward on parallel tracks: completing the design and prequalifying a contractor this fall.   We hope the alley-way access issues raised will lead to a better outcome for adjacent neighbors and city services.

All the slides from the presentation are available here.

Next
Next

Alley Design Options - Pre-Read