The South End Landmark District Commissioners Approved the Proposed Library Park Redesign; Construction to Start in June

On April 3, the South End Landmark District Commission approved a revised proposal for the redesign of  Library Park, as presented by the Boston Parks Department (see below). With their approval, came a compliment from the commissioners: "Thank you for having heard us," they told the Parks Department team. Construction is scheduled to start in June. 

At the previous presentation to the SELDC in January, project director Lauren Bryant was asked to come back with an amended proposal to include the commissioners' concerns about protection of the park's oak trees root systems, easy flow of foot traffic unimpeded by park furniture and an upgraded, more interesting hardscape that would include some details of typical South End materials like brick, slate or bluestone. The redesign of the redesign was different enough to require a second public hearing about Library Park's future, which was held at the South End library on March 22. The commissioners praised the more dynamic design and the care that was taken to protect the trees. 

The proposed re-design for Library Park that was presented to the South End Landmark District Commission on Tuesday, April 3

The proposed re-design for Library Park that was presented to the South End Landmark District Commission on Tuesday, April 3

The March 22nd public hearing solicited a number of comments, including a request to create more intimate spaces through seating and paving areas. There was a question about what to do with the granite blocks that are a play opportunity for kids, but uncomfortable to sit on; a request to inset tables with game boards; and a concern that the seating feels restrictive given that it lines both sides of the plaza. The single chairs of the current park appear to be in good shape and will be re-used and matched in style with additional curved benches, cafe tables and chairs. The oak trees will be pruned.

A large part of the work will be devoted to improving the park's infrastructure, including the clean-up of the site, underneath which there is expected to be a great deal of remnants from previous housing, including oil tanks and a lot of bricks. The soil will be improved and re-graded to enhance future landscaping. Another important aspect of the reconstruction will be groundwater management and water filtration to benefit root systems of trees, shrubs and plantings.  

At the first public hearing in November last year, Parks Department's Bryant and Brandon Kunkel, landscape architect with the Weston & Sampson design and engineering firm, presented attendees with three proposals. The one below was favored by the audience and was presented to Landmarks in January, but has been altered to comply with Landmarks's comments.  

The re-design of Library Park proposed in January but not accepted by South End Landmark commissioners concerned about root system protection, foot traffic flow and the quality of the concrete hardscape.

The re-design of Library Park proposed in January but not accepted by South End Landmark commissioners concerned about root system protection, foot traffic flow and the quality of the concrete hardscape.

After deducting the cost of design services, the remaining budget for the reconfiguration is $115,000, a small amount, which will be augmented with private fundraising efforts by the Friends of the South End Library until a more comprehensive renovation of library and park will take place in the next few years. Further information about the current project can be obtained at the Parks Department website, linked here.